Major Maintainance of ĠzaydaĢ Power Plant Steam Turbin
5 MW Siemens steam turbine major maintainance has been completed in the scope of maintainence agreement signed between Siemens Turkey under Siemens and Izaydas supervisorship. Applied works are summarized as below:
Controlling of steam turbine, disassembly, maintainance and installation of reglaj valves, sanding of 4th and 5th stage rotor ranges, replacing pinyon and big geared dample, disassembly of isolation damper and replacing with the new one, maintainance of rotor,