Enka Adapazarı Gebze Power Plants Unit 12 100.000 Hours Major Maintenance

Enka Adapazarı Gebze Power Plants Unit 12 100.000 Hours Major Maintenance

The works are as follows:

12X steam turbine unit,

  • Disassembly of HP, IP and LP turbines,
  • Dismantlator and maintenance of the generator,
  • HP ve IP türbin valf ve aktuatörlerinin demontajı, mekanik atölye de bakımı,
  • Dismantling the LP turbine blades-assembly work,
  • HP and IP turbine blade maintenance-change work and sealing rings installation,
  • HP and IP Level spray isolation studies,
  • Main lubrication Pump Maintenance,
  • Main lubrication Unit exchangers, filters and pumps maintenance,
  • Pump-pit unit cooling water pumps maintenance work,
  • BOP unit and boiler pumps dismantling and maintenance work,
  • To manufacture suitable apparatus in mechanical workshop,
  • In the 12A Unit, gas turbine element support was provided for the major maintenance performed by General Electric.
  • In the 12B Unit, the major maintenance carried out by General Electric was provided with gas turbine element support.
  • All scaffolding works in the field
  • All isolation works in the field
Employer:
ENKA
Reference Place:
Adapazarı
Date of Contract:
2013
Reference Scope:
Enka Adapazarı Gebze Power Plants 12 Gebze Unit 100,000 hours of major maintenance work has been completed with the supervision of Enka Power, Alstom Power and General Electric with a team of 240 people. The units are switched on smoothly.