Enka Adapazarı Gebze Power Plants Unit 12 100.000 Hours…
The works are as follows:
12X steam turbine unit,
Disassembly of HP, IP and LP turbines,
Dismantlator and maintenance of the generator,
HP ve IP türbin valf ve aktuatörlerinin demontajı, mekanik atölye de bakımı,
Dismantling the LP turbine blades-assembly work,
HP and IP turbine blade maintenance-change work and sealing rings installation,
HP and IP Level spray isolation studies,
Main lubrication Pump Maintenance,
Main lubrication Unit exchangers, filters and pumps maintenance,
Pump-pit unit cooling water pumps maintenance work,
BOP unit and boiler pumps dismantling and maintenance work,
To manufacture suitable apparatus in mechanical workshop,
In the 12A Unit, gas turbine element support was provided for the major maintenance performed by General Electric.
In the 12B Unit, the major maintenance carried out by General Electric was provided with gas turbine element support.
All scaffolding works in the field
All isolation works in the field
Employer:
ENKA
Reference Place:
Adapazarı
Date of Contract:
2013
Reference Scope:
Enka Adapazarı Gebze Power Plants 12 Gebze Unit 100,000 hours of major maintenance work has been completed with the supervision of Enka Power, Alstom Power and General Electric with a team of 240 people. The units are switched on smoothly.