Employer:
Siemens
Reference Place:
Çanakkale
Date of Contract:
2013
Reference Scope:
The 22.5 MW Siemens T 6259 NK50 / 90 steam turbine major maintenance works of EnerjiSA Elektrik Üretim A.Ş. were successfully completed and the turbine was commissioned without any problems. Maintenance works are as follows > Dismantling and maintenance of steam turbine body, fixed blade carriers, turbine rotor and bearings,> Dismantling and maintenance of gearbox,> Dismantling of generator rotor and bearings,> Dismantling, cleaning and maintenance of generator cooler,> Insulation tests of generator rotor and stator,> Dismantling and maintenance of turbine valves,> Turbine housing, fixed blade carriers, blasting of rotors, nuts, studs and bolts,> All assembly work after maintenance,> Mechanical work support during commissioning.