The 22.5 MW Siemens T 6259 NK50 / 90 steam turbine major maintenance works of EnerjiSA Elektrik Üretim A.Ş. were successfully completed and the turbine was commissioned without any problems. Maintenance works are as follows
At the Enerjisa Bandırma Combined Cycle Power Plant with a total installed capacity of 930 MWe, the maintenance work for the Mitsubishi M701F gas turbines with a power of 303.3 MW was completed under the supervision of Enerjisa and Mitsubishi.
The maintenance of Mitsubishi M701F type gas turbines at the Enerjisa Bandırma Natural Gas Power Plant with an installed capacity of 919 MW has been completed with the supervision of Enerjisa and Mitsubishi with our team of gas turbine technicians, I&C technicians and Mitsubishi.
Employer: Çolakoğlu Ova Elektrik Reference Location: Dilovası Kocaeli Contract Date: 2013 Reference Scope: General Electric gas tube major maintenance works at 250 MW combined cycle power plant in Ova Elektrik
General Electric gas tube major maintenance works at Ova Elektrik 250 MW combined cycle power plant were completed under Ova Elektrik and GE supervision. The works are as follows
The maintenance work of the Siemens brand steam turbine with a capacity of 30 MW at Camiş Elektrik Üretim C.O
Bursa Orhaneli Thermal Power Plant 210 MW K210-130 LMZ Steam Turbine maintenance works have been completed under the supervision of Siemens.
Bursa-EÜAŞ 1400 MW Natural Gas Cycle Power Plant 30.000 hours revision of 1 gas turbine was completed as a joint venture under the guarantee of Mitsubishi company.
Within the scope of the framework maintenance contract with Siemens Turkey Bursa Entek Power Plant 25 MW Siemens steam turbine maintenance is completed by Siemens of supervisors.
At Ankara Bilenerji Power Plant, maintenance work for CKD Energo brand 10.18 MW turbine generator was completed with our generator supervisor, mechanical, I&C and scaffolding team.