Enka Adapazarı Gebze Plants 11 Gebze unit 100,000 hours major maintenance work was completed with our team of 280 people in the supervision of Enka Power, Alstom Power and General Electric. The units are switched on smoothly.
The works are as follows:
- 11X Steam Turbine Unit,
- Disassembly of HP, IP and LP turbines,
- Dismantlator and maintenance of the generator,
- Disassembly of the HP and IP turbine valves and actuators, maintenance of the mechanical workshop,
- Dismantling the LP turbine blades-assembly work,
- HP and IP turbine blade maintenance-change work and sealing rings installation,
- HP and IP Level spray isolation studies,
- Main lubrication Pump Maintenance,
- Main lubrication Unit exchangers, filters and pumps maintenance,
- Maintenance and installation of Oil Cooler pumps and Filters Dismantation
- Dismantation, cleaning and installation of Oil cooler plates
- Realization of oil Flushing and Oil tank drain operation and cleaning
- Pump-pit unit cooling water pumps maintenance work,
- BOP unit and boiler pumps dismantling and maintenance work,
- To manufacture suitable apparatus in mechanical workshop,
- In the 11A unit, major maintenance by General Electric provided gas turbine element support.
- In the 11B unit, major maintenance by General Electric provided gas turbine element support.
- All scaffolding works in the field
- All insulation works in the field