Employer:
Enka Power
Reference Place:
İzmir
Date of Contract:
2009
Reference Scope:
1520 MW ENKA İzmir Aliağa power plant, which we provide continuous maintenance services, is in the 1st. The 48,000 hours major maintenance work of the 2nd and 2nd unit steam turbines and generators was completed under the supervision of Alstom and ENKA and the plant was commissioned without any problems.